TRAFFIC UPDATE: AUGUST AND SEPTEMBER LANE CLOSURES

AUGUST AND SEPTEMBER LANE CLOSURES

 

Beginning August 25, various lane closures will take place to support construction efforts. The schedule is as follows:

  • 8/25 - Mockingbird Station driveway and 2 westbound right lanes, 9-11 AM
  • 8/26-8/29 - The Highlands driveway, periodically during day; eastbound right lane (detour in place)
  • 8/29 - Partial Mockingbird Station driveway with traffic reduced to 1 lane, 7 AM to 10 AM
  • 8/30 - Mockingbird Station driveway, 7PM-7 AM
  • 8/31 - All westbound lanes and Mockingbird Station driveway, 8 PM-5AM
  • 9/7 - All eastbound lanes and MB Station driveway, 8 PM to 5 AM

For progress photos and up-to-date information on area closures, visit the Bridge website at http://www.universitycrossingbridge.com.